Disposal Well Facility Pad and Surface Water Pond
Working on a Tight Site with Many Stakeholders Requires Elevated Communication.
With site boundary constraints and less than ideal topography for an easy cut/fill earthworks balance, Journey worked closely with the Client to find a cost-effective design and created a staged approach to the construction in order to minimize the amount of material needing to be moved. The strategic location and planning of the surface water pond saved thousands of cubic meters of material being needed for construction, yet still achieved the environmental requirements for surface water management. This collaborative approach with the Client and Contractor reduced the overall cost of the project and helped keep the development of the disposal facility on schedule.